HMP Pentonville, London

HMP Pentonville, London

Client HM Prison Services
Project HMP Pentonville
Approved Contractor Breyer Group PLC
Type of works: supply of 700m² Bauder Single Ply Thermoplan-T System

Completed in 1842, HMP Pentonville has remained in use since opening, experiencing many stages of refurbishment throughout the decades. In 2003, the existing asphalt deck above the kitchens was in need of a complete refit with the building having to remain in use throughout the refurbishment of the roof.

A thermographic survey revealed significant levels of water trapped beneath the deck, a problem resolved by a specialist contractor removing the water to ensure the deck met Bauder’s standards before commencement of works.

The refurbishment required the removal of redundant machinery and the introduction of defined walk ways. All works were completed in six weeks with the roof area being totally transformed.

Add to Project Board

Create a new project board: