Bespoke washrooms for Sudbury Primary School staff area

Bespoke washrooms for Sudbury Primary School staff area

IGLOOS was asked to create a solution for renovating four staff washroom areas at Sudbury Primary School.

The existing rooms required building work to reshape for their new intended use. The existing were ripped out, walls were plastered and new ceilings and lighting system including PIR sensors were installed.

Bespoke WC cubicles were specified for the project, these had 2450 floor to ceiling height with independent light and emergency battery back-up and ventilation points. Moisture-resistant melamine faced chipboard (MFC) panels were chosen for the cubicles.

IGLOOS also supplied Corian® vanity units with undermounted basins and contemporary infra-red taps and floor to ceiling IgPS access panelling systems with electronic infra-red flush buttons.