This 9 storey Travelodge hotel building in Liverpool provided a number of design and engineering challenges which Kingspan Steel Building Solutions overcome during the detailed design stage. David Smart (Construction Manager for Marcus Worthington) says “The main advantage for the KingBuild System for this tight Liverpool City Centre site were, speed of erection, efficient working, minimal waste with good back up service from Kingspan’s design and onsite team."

Project Value: Kingspan Steel Building Solutions contract value - £750k

Project Size: 141 no. bedroom hotel built over a two storey podium creating a retail unit and cafe/bar on the ground and first floor respectively.

Construction: Load Bearing structure with composite concrete floors erected in 15 weeks, opened in Spring 2012

Finishes: Lightweight cladding façade treatments in contrasting colours were used to create a stylish and contemporary exterior finish.

Add to Project Board

Create a new project board:


View The Kingbuild System (KBS) Product Entry
Kingspan Steel Building Solutions

Kingspan Steel Building Solutions

Kingspan Steel Building Solutions is Europe's leading manufacturer and innovator of modern methods of construction in steel, providing high performance solutions to the public, private and commercial sectors.
View company profile
T0121 753 7050
F0121 753 5187
Eenquiries@kingspansbs.com
WVisit Kingspan Steel Building Solutions's website
 Unit 2 & 3, Progress Works, Bromley Street, Birmingham, B9 4AL

Categories

Structural frames

Make an enquiry to

You may also be interested in this related Case Study: Case Study: West Downs Campus, University of Winchester Read Now