Target Field, Minneapolis, Minnesota

Target Field, Minneapolis, Minnesota

Client: Minnesota Ballpark Authority (MBA)
Architect: Populous
Structural engineers: Van Sickle, Allen & Associates
Contractor: M.G. McGrath Architectural Sheet Metal
Type of works: manufacture and installation of Lindapter's steelwork fixings for the Minnesota Twins' ballpark.

The new $425 million Target Field ballpark features an inspiring 1,988 ton steel sunshade canopy that sweeps around the stadium, with a 7,432 m2 glistening soffit safely suspended overhead with Lindapter steelwork fixings.

The 40,000 seat, open-air Target Field is the new home of Minnesota Twins, an American professional baseball team based in Minneapolis, Minnesota. The architecturally stunning curved canopy presented a challenge to the connection design due to the connecting beams varying in size and angle throughout. The engineers also had to meet a vital criterion of accommodating up to 22.3kN of wind load, while the contractor favoured a simple to install, universal connection that could be used on both primary and secondary steel sections.

“We needed a connection scheme with a lot of flexibility because we were attaching to in-place structural steel and the soffit framing (particularly as it curves) is not necessarily parallel to the structural steel.” stated Kelsey F. Brown, PE, SE Principal at Van Sickle, Allen & Associates.

“We were looking for a user friendly connection system that eliminated the touch-up hassles. We analysed it and picked Lindapter.” said Mike McGrath, Vice President of Operations at M.G. McGrath Architectural Sheet Metal.

Lindapter provided a single solution that exceeded these requirements with the Type LR Girder Clamp connection system, independently approved to a safe working load of 58.8kN at a 5:1 factor of safety. The self-adjustable assembly is compatible with flange thicknesses of 3 to 20mm, while an over-sized slotted location plate enabled the simple adjustment to fit variations in beam width and connection angle. The efficient connection allowed the canopy risers to be easily aligned into position, allowing a faster installation in comparison to more time consuming conventional methods such as drilling, or repeated tack welding and grinding, thereby reducing on-site costs.

As the installation did not require hot working it was not necessary to renew the corrosion protection at over 1,200 connection points and more importantly, the structural integrity of the primary steel was maintained. As the canopy construction largely consisted of elevated and overhead work, eliminating drilling, welding and grinding contributed greatly to the overall safety of the project.

For further information please call 01274 521 444 or visit www.lindapter.com.

Add to Project Board

Create a new project board:


View Lindapter Catalogue PDF

Lindapter International

View company profile
T(01274) 521444
F(01274) 521130
Eenquiries@lindapter.com
WVisit Lindapter International's website
 Lindsay House, Brackenbeck Rd, Bradford, W Yorkshire, BD7 2NF

Make an enquiry to Lindapter International

You may also be interested in this related Case Study: Geberit is The Perfect Fit at Dublin's Two Oaks Residential Development Read Now